TROLLEYBUSES

Current situation.

Active network: 18.2 km equivalent (15.2 km double track, 4.5 km single track, 0.7 km depot acces double track).
Inactive network: 5.3 km double track.
Total network: 23.4 km equivalent (20.5 km double track, 4.5 km single track, 0.7 km depot acces double track).
Routes: 3(7.2 km), 5b(7.1 km), 7(7.8 km), 8(6.9 km), 30(7.9 km), 33(3.7 km).
The longest routes are indicated in green while the shortest ones are in red.


2009
TROLLEYBUSES

Situation in 2009.

Active network: 21.8 km equivalent (18.9 km double track, 4.5 km single track, 0.7 km depot acces double track).
Inactive network: 1.6 km double track.
Total network: 23.4 km equivalent (20.5 km double track, 4.5 km single track, 0.7 km depot acces double track).
Routes: 3(7.2 km), 5b(7.1 km), 7(7.8 km), 8(6.9 km), 10(8.2 km), 30(7.9 km), 33(3.7 km).


2006
TROLLEYBUSES

Situation in February 2006.

Active network: 24.4 km equivalent (19.0 km double track, 9.5 km single track, 0.7 km depot acces double track).
Inactive network: 5.5 km double track.
Total network: 29.9 km equivalent (24.5 km double track, 9.5 km single track, 0.7 km depot acces double track).
Routes: 1(8.2 km), 1b(7.4 km), 2(6.5 km), 3(6.2 km), 5b(6.9 km), 7(8.5 km), 30(8.0 km), 32(4.4 km), 33(3.7 km).


2003
TROLLEYBUSES

Situation in September 2003 according to Strassenbahn Atlas Romania 2004.

Active network: 32.7 km equivalent (26.3 km double track, 11.4 km single track, 0.7 km depot acces double track).
Inactive network: 2.3 km equivalent (2.0 km double track, 0.6 km single track).
Total network: 34.9 km equivalent (28.3 km double track, 11.9 km single track, 0.7 km depot acces double track).
Routes: 1(8.2 km), 1b(9.3 km), 2(7.0 km), 2b(5.3 km), 3(6.1 km), 5(8.3 km), 7(8.5 km), 9(8.1 km), 10(8.1 km), 10b(4.4 km), 31(5.6 km), 32(4.4 km), 33(3.8 km).


1987
TROLLEYBUSES

Situation before works on the New Civic Center began, 1987.

Active network: 33.0 km equivalent (27.5 km double track, 10.1 km single track, 0.4 km depot acces double track).
Inactive network: 0.1 km equivalent (0.2 km single track).
Total network: 33.1 km equivalent (27.5 km double track, 10.3 km single track, 0.4 km depot acces double track).
Routes: 1(7.7 km), 1b(6.2 km), 2(7.0 km), 2b(5.7 km), 3(6.0 km), 3b(4.1 km), 4(3.8 km), 5(8.3 km), 6(5.4 km), 7(8.4 km), 8(6.9 km), 9(8.1 km), 9b(6.0 km), 10(8.1 km), 10b(4.4 km), 16(6.0 km), 31(5.7 km), 31b(4.2 km).


1974
TROLLEYBUSES

Situation in 1974 according to the Turist Guide from that year.

Active network: 20.9 km equivalent (16.5 km double track, 7.9 km single track, 0.4 km depot acces double track).
Routes: 1(7.7 km), 2(7.0 km), 3(6.0 km), 4(3.1 km), 4b(4.9 km), 5(7.7 km), 6(3.2 km), 7(7.6 km), 9(7.5 km), 9b(5.6 km).


1967
TROLLEYBUSES

Situation in 1967 according to a German guide.

Active network: 18.4 km equivalent (15.5 km double track, 5.9 km single track).
Routes: 1(7.7 km), 2(5.1 km), 3(6.0 km), 4(4.0 km), 5(7.6 km), 7(3.2 km), 9(3.3 km).